icon new connection for multi unit

 Before you proceed

Multi Unit New Connection

You have chosen to apply for a Multi-Unit Development. This application applies to connections of 2 or more houses, apartments, or commercial/industrial units.

In order to provide you with a valid quote, accurate information must be provided in your application.

Project Time Frame & Typical Pricing

Once you have all of the documentation required, the application process should only take 10 to 15 minutes.

We aim to provide a quotation and Development Agreement within 90 business days of receiving a completed application.

Connection costs are calculated on the basis of standard CRU approved charges detailed in the document Charges for Connection to the Distribution System PDF | 178 KB.  Further information about connection charges can be found in the ESB Networks DAC Statement of Charges PDF | 538 KB.

For connections that support large electrical loads, considerable time may be required to establish the most appropriate connection method, determine costs and carry out the work required. Project time frames will vary depending upon the extent of the work required, material lead times, and the Customer’s works schedule.

While we will make every effort to meet these target timeframes,  you may experience delays due to current high demand.  We apologise for any inconvenience this may cause you.

 

Mandatory Information & Documentation

In order to complete your application the following are required:

Multi Unit Connection Check List

Continue to Application

Get in Touch
PHONE
1800 372 757