What are the steps involved?

In some circumstances you'll need to get an electricity pole or an overhead electricity line moved. When you do these are the steps involved:

  • Get an Ordnance Survey Map and Site Plan
  • Make an application
  • Application is assessed and a charge may apply

Step by step guide

Get an Ordnance Survey Map And Site Plan

Using an Ordnance Survey map (scale 1:2500-1:10560) of your site and detailed site plan (scale 1:100-1:500) showing the layout of any new or existing buildings, mark the exact location of the line or pole to be moved with a red pen.

 

​If the work being done requires planning permission, you must provide details of the permission.

Apply
Apply online

 

Or

 

Apply offline

 

Please note we no longer process Relocate a Pole or Line (NW1) applications emailed to ESB Networks.

 

Download the form Application for Relocation of Pole or Line (NW1) or call 1800 372 757 or +353 21 2386555 (from outside Ireland), to request a copy.


Send the completed form together with the ordnance survey map and the site plan to:


ESB Networks DAC,

New Connections,

Sarsfield Road,

Wilton Cork,

T12E367,

Ireland

Application Assesment

Your request will be sent to a Design Officer in your local ESB Networks Office. The application will be assessed and our Design Officer will contact you to discuss the next steps and advise you if a charge is applicable.