In our Networks for Net Zero strategy, ESB Networks has committed to delivering a net zero ready electricity distribution network by 2040 to enable Ireland to achieve its legally binding net zero target by 2050. A key action in our strategy is to publish a ten-year Distribution Network Development Plan (DNDP) as required under the Clean Energy Package Directive (EU) 2019/944.
Part 1: A Summary Document and Methodology Statement.
Part 2: A Distribution Network Development Report (DNDR) providing detailed information on investment projects in each distribution network area that will add capacity.
A consultation was held in Q3 2025, please see our response to our stakeholders below.
The Network Scenario Headroom Report (NSHR) consists of two capacity workbooks for both demand and generation on the distribution system. The publication of these workbooks marked the first step in our plan to publish the Distribution Network Development Plan (DNDP). Publication of the DNDP is a requirement of EU Directive (2019/944) which stipulates that Distribution System Operators should publish a Network Development Plan every two years. The purpose of the plan is to provide a useful source of information on the future plans for reinforcement and flexibility service needs on our electricity network.
Please see below the Demand Capacity Headroom Report 2025. The Generation Capacity Headroom report is due for publishing in Q1 2026.
Note: Users should download a copy of the workbooks to a local drive in order to use the workbooks effectively.
The capacity workbooks provide an indication of the available transformer capacity at substations. It does not guarantee the same capacity is available in the upstream networks such as the 38 kV network feeders or transmission system bulk supply points. It cannot be relied upon in isolation to assess the viability of a connection to a premises. Whilst we use reasonable endeavours to ensure that the capacity workbooks and related information are accurate, we do not warrant, and do not accept any responsibility or liability for, the accuracy or completeness of the content or for any consequence or loss which may arise from reliance on the capacity workbooks or related information. The available capacity figures will be updated annually. The legal disclaimer terms and conditions for use of our website apply to the capacity workbooks and related information.
This workbook provides indicative "headroom" capacity available for new demand connections at existing 110 kV and 38 kV substations. Forecasts are produced for every year up to 2030, and then for every five years after that out to 2050. The workbook indicates the spare or “headroom” capacity available at a station under four different growth rate scenarios. Note that the information provided is indicative. There can be upstream network limitations on High Voltage (HV) feeders and transmission system feeders that will limit capacity at local substations. In order to secure capacity for a new connection, customers are advised to follow the new connection application process available on the ESB Networks website www.esbnetworks.ie.
Demand Capacity Headroom Report 2024 included projects that are planned for the Price Review 5 (PR5) period to 2025. Demand Capacity Headroom Report 2025 includes reinforcement projects planned for the PR6 period to 2030.
Firm capacity is the capacity that a HV station can sustain over a prolonged period under both normal feeding operation and during an outage due to a fault or maintenance of a transformer at a station. Non-firm capacity is additional capacity in excess of the firm capacity that could also be provided at a station. During an outage of a transformer, non-firm capacity is available if there are adequate load transfer arrangements in place to transfer demand to adjacent stations or there is flexible load at the station that can be used to reduce demand within the required timeframe.
Customers are encouraged to engage early with ESB Networks if they are planning a new development that will require a connection to the electricity network.
To secure capacity for a new connection customer are advised to follow the new applications process available on the ESB Networks website
ESB Networks' network planners must carry out a detailed network study for each application before a connection is issued.
If you have any feedback or comments on the headroom capacity workbooks please contact us at the following email address development.plans@esbnetworks.ie