Skip to Content
For emergencies: Call 1800 372 999
Gaeilge

What happens if I have not secured planning permission after receiving a connection assessment?

If you have not secured planning permission within the two years following connection assessment issuance, the connection assessment will be deemed lapsed, but your application will remain open for processing subject to planning permission grant.  Your project will then be re-studied at no additional cost at the next available opportunity and may be processed on either a batch or non-batch basis.  You will need to pay the balance of the application fee before you will receive your connection agreement.