I don't have planning permission for my project. When do I need to pay the application fee balance?

The application fee balance will only be requested if your community-led project has secured planning permission. Once you have notified us that planning permission has been confirmed and have completed the relevant planning permission section of the NC5 or NC5A form, we will request the application fee balance and you will have one month to make this payment. Once payment has been received, we will issue you with your connection agreement.