How should I prepare for the early engagement meetings?

In advance of the meeting, you will need to consider if you plan to build your own dedicated connection (known as contestable builds) or request ESB Networks to build the connection to the grid (known as non-contestable. You should also consider whether you plan to connect via overhead line or underground cable, as the connection costs will vary depending on the preferred connection type. The grid connection will always be based on the Least Cost Technically Acceptable (LCTA) connection method (generally an overhead line connection).