How are community-led projects prioritised into batches?

If you have an existing application submitted before ECP-2 and now wish to apply as a community-led project, you must complete a Community-led Project Declaration Form and your project may be prioritised into a batch by the planning permission grant date or by received complete date (if you have not secured planning permission).

If you are submitting a new application, you will be prioritised by planning permission grant date (if you have secured planning permission) and then by earliest received complete date.  Please find more information on what is meant by "received complete date" at this link.