Fluid Filled Cable Repairs -  Map 

 

webpack-start
Site ID Repair Date Circuit Name Status Coordinates
Site 1 01/05/19 Camden Row - Newmarket 38 kV Environmental Assessment Underway. Cable Repaired. 53.336498 -6.266710
Site 2 01/02/19 Fairhill - Kilbarry 38 kV Environmental Assessment Underway. Cable Repaired. 51.906636 -8.481197
Site 3 01/11/18 Harold's Cross - Ringsend 110 kV Environmental Assessment Underway. Cable Repaired. 53.333733 -6.246258
Site 4 01/11/18 Dodder Rd - Templeogue 38 kV Environmental Assessment Underway. Cable Repaired. 53.299966 -6.285522
Site 5 01/08/18 Ballymun - Fairview 38 kV Environmental Assessment Underway. Cable Repaired. 53.376361 -6.252690
Site 6 01/08/18 Ballymun - Fairview 38 kV Environmental Assessment Underway. Cable Repaired. 53.377131 -6.256703
Site 7 01/02/18 Inchicore - Poolbeg One 220 kV Environmental Assessment Underway. Cable Repaired. 53.335496 -6.263595
Site 8 01/09/16 Carrickmines - poolbeg 220 kV Environmental Assessment Underway. Cable Repaired. 53.337445 -6.219208
Site 9 01/07/16 Inchicore - Poolbeg Two 220 kV Environmental Assessment Underway. Cable Repaired. 53.331239 -6.257446
Site 10 01/08/15 Kingsbridge - Watling Street 38 kV Environmental Assessment Underway. Cable Repaired. 53.346557 -6.291474
Site 11 01/08/15 Clontarf - East Wall Road 38 kV Environmental Assessment Underway. Cable Repaired. 53.364212 -6.227787
Site 12 01/06/15 Carrickmines - Poolbeg 220 kV Environmental Assessment Underway. Cable Repaired. 53.279337 -6.197939
Site 13 01/04/15 Dodder Rd - Templeogue 38 kV Environmental Assessment Underway. Cable Repaired. 53.298177 -6.304365
Site 14 01/03/15 Deansgrange - Sallynoggin 38 kV Environmental Assessment Underway. Cable Repaired. 53.277900 -6.140296
Site 15 01/02/15 Finglas - Merville 38 kV Environmental Assessment Underway. Cable Repaired. 53.396590 -6.305482
Site 16 01/01/15 Unidare - Whitehall 38 kV Environmental Assessment Underway. Cable Repaired. 53.376833 -6.255391
Site 17 01/11/14 Francis Street - Harold's Cross 110 kV Environmental Assessment Underway. Cable Repaired. 53.329019 -6.275493
Site 18 01/11/14 Francis Street - Inchicore 110 kV Environmental Assessment Underway. Cable Repaired. 53.334060 -6.331711
Site 19 01/06/14 Inchicore - Marrowbone Lane 38 kV Environmental Assessment Underway. Cable Repaired. 53.339390 -6.288288
Site 20 01/04/13 Bedford Row - Sheriff Street 38 kV Environmental Assessment Underway. Cable Repaired. 53.347433 -6.256866
Site 21 01/10/12 Carrickmines - Poolbeg 2012 Environmental Assessment Underway. Cable Repaired. 53.279337 -6.197939
Site 22 01/03/12 Finglas - Merville 38 kV Environmental Assessment Underway. Cable Repaired. 53.382100 -6.291527
Site 23 01/09/11 Bedford Row - Francis Street 38 kV Environmental Assessment Underway. Cable Repaired. 53.343645 -6.270828
Site 24 02/07/05 Blackrock - Ringsend 110 kV Environmental Assessment Underway. Cable Repaired. 53.311290 -6.200422
Site 25 01/11/09 Dodder Rd - Templeogue 38 kV Environmental Assessment Underway. Cable Repaired. 53.301350 -6.289162
Site 26 01/02/19 Deansgrange - Sallynoggin 38 V Environmental Assessment Underway. Cable Repaired. 53.277673 -6.140749
Site 27 01/11/12 Marina - Trabeg Two 110 kV Environmental Assessment Underway. Cable Repaired. 51.898370 -8.446258
Site 28 01/11/11 Pembroke - Ringsend 38 kV Environmental Assessment Underway. Cable Repaired. 53.342335 -6.221777
Site 29 01/02/10 Unidare - Whitehall 38 kV Environmental Assessment Underway. Cable Repaired. 53.378532 -6.264743
Site 30 01/07/10 Francis Street - Inchicore 110 kV Environmental Assessment Underway. Cable Repaired. 53.336143 -6.312076
Site 31 01/11/09 Inchicore - Marrowbone Lane 38 kV Environmental Assessment Underway. Cable Repaired. 53.337618 -6.299221
Site 32 01/09/09 Harold's Cross - Ringsend 110 kV Environmental Assessment Underway. Cable Repaired. 53.334039 -6.245266
Site 33 01/04/09 Francis Street - Camden Row 38 kV Environmental Assessment Underway. Cable Repaired. 53.340776 -6.267908
Site 34 01/03/09 Francis Street - South King Street 38 kV Environmental Assessment Underway. Cable Repaired. 53.340878 -6.267310
Site 35 01/03/09 Blackrock - Ringsend 110 kV Environmental Assessment Underway. Cable Repaired. 53.313043 -6.201906
Site 36 01/11/08 Inchicore - Marrowbone Lane 38 kV Environmental Assessment Underway. Cable Repaired. 53.338855 -6.289258
Site 37 01/11/08 Parkview - Ringsend 38 kV Environmental Assessment Underway. Cable Repaired. 53.344594 -6.228027
Site 38 01/10/08 Marina - Trabeg Two 110 kV Environmental Assessment Underway. Cable Repaired. 51.896000 -8.445610
Site 39 01/10/08 Francis Street - Inchicore 110 kV Environmental Assessment Underway. Cable Repaired. 53.334488 -6.326322
Site 40 01/09/08 Blackrock - Ringsend 110 kV Environmental Assessment Underway. Cable Repaired. 53.305472 -6.185486
Site 41 01/02/08 Carrickmines - Poolbeg 220 kV Environmental Assessment Underway. Cable Repaired. 53.302764 -6.210796
Site 42 01/02/08 Donnybrook - Pembroke 38 kV Environmental Assessment Underway. Cable Repaired. 53.322745 -6.233559
Site 43 01/09/08 Carrickmines - Pottery Road 110 kV Environmental Assessment Underway. Cable Repaired. 53.255057 -6.177457
Site 44 01/09/07 Maynooth - Turlough Hill 220 kV Environmental Assessment Underway. Cable Repaired. 53.043925 -6.405978
Site 45 01/08/07 Francis Street - Inchicore 110 kV Environmental Assessment Underway. Cable Repaired. 53.334286 -6.328249
Site 46 01/04/07 East Wall Road - McDermott 38 kV Environmental Assessment Underway. Cable Repaired. 53.354678 -6.251413
Site 47 01/03/07 East Wall Road - Ringsend Environmental Assessment Underway. Cable Repaired. 53.341256 -6.208134
Site 48 01/12/06 Blackrock - Ringsend 110 kV Environmental Assessment Underway. Cable Repaired. 53.312551 -6.201558
Site 49 01/08/06 Roolbeg - Ringsend TF4 110 kV Environmental Assessment Underway. Cable Repaired. 53.338319 -6.189804
Site 50 01/11/05 East Wall Road - McDermot 38 kV Environmental Assessment Underway. Cable Repaired. 53.357975 -6.234103
Site 51 01/11/05 Marina - Trabeg Two 38 kV Environmental Assessment Underway. Cable Repaired. 51.895938 -8.445898
Site 52 01/05/05 Parkview - Ringsend 38 kV Environmental Assessment Underway. Cable Repaired. 53.341284 -6.208127
Site 53 01/03/05 Marrowbone Lane - Newmarket 38 kV Environmental Assessment Underway. Cable Repaired. 53.336767 -6.282069
Site 54 01/12/04 East Wall Road - North Wall 38 kV Environmental Assessment Underway. Cable Repaired. 53.350603 -6.210961
Site 55 01/11/04 Francis Street - Inchicore 110 kV Environmental Assessment Underway. Cable Repaired. 53.333758 -6.334224
Site 56 01/11/04 Fairhill - Kilbarry 38 kV Environmental Assessment Underway. Cable Repaired. 51.907389 -8.482369
Site 57 01/07/04 Inchicore - Poolbeg Two Environmental Assessment Underway. Cable Repaired. 53.332914 -6.339321
Site 58 01/04/04 East Wall Road - Fairview 38 kV Environmental Assessment Underway. Cable Repaired. 53.354745 -6.228791
Site 59 01/03/04 Ballymun - Fairview 38 kV Environmental Assessment Underway. Cable Repaired. 53.364976 -6.230280
Site 60 26/06/05 Pembroke - Ringsend 38 kV Environmental Assessment Underway. Cable Repaired. 53.339201 -6.230703
Site 61 01/07/04 Dennehy's Cross - Liberty Street 38 kV Environmental Assessment Underway. Cable Repaired. 51.888760 -8.503053
Site 62 01/11/03 Blackrock - Ringsend 110 kV Environmental Assessment Underway. Cable Repaired. 53.309773 -6.195082
Site 63 01/07/03 Phibsborough - Granby Row 38 kV Environmental Assessment Underway. Cable Repaired. 53.358528 -6.271864
Site 64 01/05/03 Inchicore - Poolbeg Two 220 kV Environmental Assessment Underway. Cable Repaired. 53.335322 -6.319173
Site 65 25/06/05 Pembroke - Ringsend 38 kV Environmental Assessment Underway. Cable Repaired. 53.342236 -6.219486
Site 66 01/11/02 Finglas - Merville 38 kV Environmental Assessment Underway. Cable Repaired. 53.381787 -6.291708
Site 67 01/12/98 Finglas - Northwall 220 kV Environmental Assessment Underway. Cable Repaired. 53.350882 -6.21735
Site 68 01/11/93 Francis Street - Inchicore 110 kV Environmental Assessment Underway. Cable Repaired. 53.336102 -6.312441
FFC-2019-001 23/08/19 Bedford Row - South King Street S5(C) - Cable repaired 53.344227 -6.262380
FFC-2019-002 28/04/20 Clontarf - East Wall Road S5(C) - Cable repaired 53.370090 -6.202967
FFC-2019-003 15/10/19 Coolock - Raheny S5(C) - Cable repaired 53.386368 -6.201869
FFC-2019-004 02/09/19 Francis St - Inchicore S5(C) - Cable repaired 53.337071 -6.279194
FFC-2019-006 TBA Harold’s Cross - Ringsend S3 - Establish leak location 53.340596 -6.220574
FFC-2019-007 16/05/20 Deansgrange - Sallynoggin S5(C) - Cable repaired 53.275976 -6.149401
FFC-2019-008 17/11/19 Finglas - Merville S5(C) - Cable repaired 53.387300 -6.298316
FFC-2019-009 23/01/20 Pembroke - Ringsend S52 S5(C) - Cable repaired 53.339206 -6.230836
FFC-2019-011 TBA Kingsbridge - Watling Street S3 - Establish leak location 53.346858 -6.290889
FFC-2019-012 TBA Poolbeg - Ringsend TF4 S4 - Notification of leak 53.339189 -6.206704
FFC-2019-015 18/02/20 Dennehy's Cross - Togher S5(C) - Cable repaired 51.876808 -8.495333
FFC-2019-016 17/01/20 Bedford Row - Sheriff Street S5(C) - Cable repaired 53.347799 -6.254982
Note: S3 (Step 3) - Establish Leak Location; S4 (Step 4) - Notification of actual leak location; S5(C) (Step 5(C)) - Cable physically repaired